Y -- Coffee Pot #2 Bridge Construction - Responses to Questions

Notice Date
8/9/2018
 
Notice Type
Modification/Amendment
 
NAICS
237310 — Highway, Street, and Bridge Construction
 
Contracting Office
Department of Agriculture, Forest Service, R-2 White River National Forest, 900 Grand Ave., Glenwood Springs, Colorado, 81601, United States
 
ZIP Code
81601
 
Solicitation Number
1282D718R0006
 
Point of Contact
Lonnie D Root, , Erica Borum, Phone: 970-945-3277
 
E-Mail Address
lroot@fs.fed.us, eborum@fs.fed.us
(lroot@fs.fed.us, eborum@fs.fed.us)
 
Small Business Set-Aside
Total Small Business
 
Description
Responses to Questions The White River National Forest anticipates awarding a firm-fixed price Bridge Construction contract to perform the following scope of work: The work shall consist of what is shown on the plans, stated in the specifications, and summarized below: •Establish traffic control and detour. •Remove the existing bridge. •Excavate for the abutments. •Construct the abutments. •Construct the stream channel between abutments (step removal, grading and riprap). •Construct the timber superstructure. •Construct the approaches to the structure (embankment). •Install signs. •Seeding work. Solicitation Schedule: Synopsys Posted: 07/13/2018 Solicitation Post Date: 07/27/2018 Pre-Bid Site Visit: 08/07/2018 - Time 10:00 MST Q&A Due Date: 08/08/2018 Solicitation Close Date: 08/27/2018 - Time: 1700 MST Projected Period of Performance: Pre-Work Mandatory Meeting: 09/18/2018 Construction Start Date: 08/01/2019 In-Stream Fisheries Work Window is August 1st through September 30th Maximum Road Closure on Coffee Pot Road is 45 days Overall Period of Performance: 09/18/2018 – 11/01/2019 Expanded POP allows adequate timespan to cover Pre-Work Meeting through Invoice Processing after completion of work. Questions: All questions pertaining to this solicitation MUST be marked: 1282D718R0006 and submitted in writing and addressed to Lonnie D. Root, Contracting Officer by email at lroot@fs.fed.us no later than: 08/08/2018 No phone calls will be accepted. Proposals: Proposals from this solicitation MUST be marked 1282D718R0006 and be submitted in writing to Lonnie D. Root, Contracting Officer via either Hard Copy to the below address or by Email Hard Copy Proposals Send To: Lonnie D. Root Contracting Officer White River National Forest 900 Grand Ave Glenwood Springs, CO 81601 Email Proposals Send To: lroot@fs.fed.us Subject: Proposal 1282D718R0006 Coffee Pot Bridge Project Project Location: Eagle-Holy Cross Ranger Disctrict White River National Forest Coffee Pot Road (NFR 600) Near Deep Lake The Coffee Pot #2 bridge is located approximately 15 miles north of Glenwood Springs, Colorado, although the drive from there to the site is about 48 miles. Directions: Exit 133 off I-70 at Dotsero Travel North on Colorado River Rd (301) for 1.8 miles Turn left on Coffee Pot Rd (NFR 600) for 29 miles Turn left at Sign for "Day Use Area/Budges Resort" Just past Deep Lake in the White River National Forest Description: The Contractor shall furnish the necessary personnel, materials, equipment, services and facilities. Project includes, but is not limited to, removing and disposing of the existing bridge, excavate for the abutments, construct new abutments, construct the stream channel between abutments (Step removal, grading and riprap), construct the timber superstructure, construct the approaches to the structure (embankment), install signs and seeding work to match design plans and all other incidental items necessary to complete the work according to the contract. All construction must comply with wilderness rules and restrictions. Traditional tools will be used as much as possible; however some motorized tools and mechanical transport will be allowed. Motorized tools and mechanical transport will be restricted to the uses approved in the minimum requirements decision guide (MRDG) and minimized in the project. Set-aside: This procurement is being set-aside 100% for small business. Industry Classification System Code (NAICS) is 237310 Highway, Street and Bridge Construction and the small business size standard is $36.5 million, set-aside 100% for small business. The magnitude of the contract is between $200,000.00 and $250,000.000 Pre-Bid Proposal Conference: Date: August 7, 2018 Time: 10:00 a.m. (Mountain Time) Location: Meet onsite at Coffee Pot Bridge #2 Note: Alternatively, the Forest Service will be at the dirt lot north of the traffic circle on the Colorado River Road in Dotsero (I-70 exit 133) at 8:30am prior to driving to the project site for those wishing to caravan. Please RSVP to the pre-proposal site visit by contacting Erica Borum, 970-945-3277
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/notices/b434eed92b27b754d6722bedb0718160)
 
Place of Performance
Address: Eagle-Holy Cross Ranger District, White River National Forest, Coffee Pot Road (NFR 600) Near Deep Lake, Dotsero, Colorado, 81637, United States
Zip Code: 81637
 
Record
SN05030431-W 20180811/180809231716-b434eed92b27b754d6722bedb0718160 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.