Z -- 528A8-22-815 REPLACE CHILLER PLANT ROOF SYSTEM

Notice Date
8/2/2022 11:55:45 AM
 
Notice Type
Solicitation
 
NAICS
238160 — Roofing Contractors
 
Contracting Office
242-NETWORK CONTRACT OFFICE 02 (36C242) ALBANY NY 12208 USA
 
ZIP Code
12208
 
Solicitation Number
36C24222B0056
 
Response Due
8/15/2022 8:00:00 AM
 
Archive Date
09/14/2022
 
Point of Contact
Lester S Griffith, Contract Specialist
 
E-Mail Address
Lester.Griffith@va.gov
(Lester.Griffith@va.gov)
 
Awardee
null
 
Description
Request For Information (RFI) Samuel S. Stratton VA Medical Center Project Name: Replace Chiller Plant Roof System Project #: 528A8-22-841 Solicitation#: 36C24222B0056 August 02, 2022 RFI #1 Question #1. Please confirm that the elevation of the new roofing system will be equal to the existing elevation. This is an important question because if the new roofing is higher, we will have to remove metal and add wood blocking at the leading edge and penetrations. A change in height will also cause a lot of rebuilding at the newly installed uni-strut pipe supports. Answer: Existing elevation shall remain, no new additional blocking will be required Question #2. Please confirm that no additional blocking, support, etc. is required underneath the (1) existing pipe supports, (2) ladders, (3) other devices. If something is required, please detail what that is for each condition. Answer: No new additional blocking will be required Question #3. Please confirm the existing edge metal is to remain in place (no work). The scope of work does not describe the metal being removed, reinstalled or replaced in any way. Answer: Existing metal flashing to be reused Question #4. Please provide the requirements for re-certification of the existing portable safety rail system. Answer: Certification will be accomplished via final inspection by the VA COR Question #5. Is the contractor required to have a SSHO or QCM on site during construction, or can the Superintendent act as all three roles? Answer: The Superintendent can act as all three
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/91260be1978f4cb5b15c3cef6c4c63dc/view)
 
Record
SN06410829-F 20220804/220802230119 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.