SPECIAL NOTICE
61 -- 61--Request for Information for Station Service Trans.
- Notice Date
- 9/13/2022 12:21:15 PM
- Notice Type
- Special Notice
- NAICS
- 335311
— Power, Distribution, and Specialty Transformer Manufacturing
- Contracting Office
- UPPER COLORADO REGIONAL OFFICE SALT LAKE CITY UT 84138 USA
- ZIP Code
- 84138
- Solicitation Number
- DOIRFBO220039
- Response Due
- 10/14/2022 3:30:00 PM
- Archive Date
- 01/31/2023
- Point of Contact
- Handy, Jennifer, Phone: 435-885-3228, Fax: 435-885-3224
- E-Mail Address
-
JHandy@usbr.gov
(JHandy@usbr.gov)
- Description
- Request for Information (RFI) for Station Service transformers at Glen Canyon Power Plant The Upper Colorado Basin Regional Office of the U.S. Bureau of Reclamation is conducting market research to replace two station service transformers at the Glen Canyon Power Plant located in Page, Arizona. This is not an announcement of a Solicitation. In accordance with Federal Acquisition Regulation (FAR) 52.215-3, Request for Information for Solicitation and Planning Purposes (October 1997), this notice is issued solely for information and planning purposes. It does not constitute a Request for Proposal (RFP). The Department of the Interior (DOI) BOR intends to assess the responses to inform its decision-making. This notice is not to be construed as a commitment by the government to contract for services. The government will not pay for any information provided as a result of this notice and will not recognize or reimburse any cost associated with RFI submission. Responses to this RFI will not affect a potential offeror's ability to respond to any RFP that might follow. Please ensure that any sensitive or protected information is marked as such and the government will ensure this information is not released externally. Technical Requirements/Specifications - Please see attached file. Response: Responses are requested with the following information: 1. Offerors� name, address, DUNS/UEI number, points of contact with telephone numbers and e-mail addresses. 2. Description of transformer and voltages regulation equipment to include: o Overall equipment dimensions o Clearances on each side of equipment needed for air flow and maintenance. o Oil Volume 3. Is the voltage regulator or automatic tap changer built into the transformer? 4. If the proposed solution requires a separate unit for voltage regulation what are the dimensions and clearances for the equipment? 5. Country of manufacture of the transformer(s). Please supply documentation of the country of manufacture of the transformer(s). 6. Lead time for manufacture and delivery of transformers. Please respond by email only, send responses to the Contract Specialist, Jennifer Handy, at jhandy@usbr.gov
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/8488fc470b4d479e885a8fd7cfd6a9cb/view)
- Record
- SN06462804-F 20220915/220913230127 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |