Y -- USDA-NRCS-TX - Hickory Creek Watershed Site 11 & 14 Repairs in Denton County

Notice Date
8/5/2025 11:15:35 AM
 
Notice Type
Combined Synopsis/Solicitation
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
FPAC BUS CNTR-ACQ DIV WASHINGTON DC 20250 USA
 
ZIP Code
20250
 
Solicitation Number
12FPC325B0006
 
Response Due
8/26/2025 10:00:00 AM
 
Archive Date
09/10/2025
 
Point of Contact
Mark Domingo
 
E-Mail Address
mark.domingo@usda.gov
(mark.domingo@usda.gov)
 
Small Business Set-Aside
SBA Total Small Business Set-Aside (FAR 19.5)
 
Description
Please see attachment combined synoposis solicitation and Statement of Works (SOW) for further detials. This solicitation is a Total Small Business Set-Aside. A firm fixed price construction contract is anticipated to be awarded under Sealed Bidding in FAR Part 14. Site Visit is scheduled for 8/13/2025 at 10:00AM meeting at: 525 S. Loop 288 Suite C-1 Denton, TX 76205 A bid guarantee shall be 20% of the bid price or $3 Million, whichever is less. The estimated magnitude of the project is between $1,250,000 and $1,750,000 The upstream wave berm repair of Site 11 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The upstream wave berm repair of Site 14 will consist of stripping and stockpiling the topsoil from the embankment eroded area; performing excavation and earthfill activities to achieve the specified rock riprap subgrade; placing and anchoring geotextile fabric on the approved subgrade; placing rock riprap to the required thickness and limits as shown in the construction drawings; backfilling the toe of the rock riprap with earthen materials; blending the earthwork above the rock riprap into the existing embankment; establishing vegetation; and reconstructing the fence above the rock riprap. The existing, constructed plunge basin has experienced erosion along the side slopes of the basin and outlet channel. To prevent/retard future erosion, the basin will be armored with a 2 feet thick blanket of rock riprap.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/0d39708047754981a96834225a12fd90/view)
 
Place of Performance
Address: Denton, GA, USA
Country: USA
 
Record
SN07536709-F 20250807/250805230045 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.