COMMERCE BUSINESS DAILY ISSUE OF MAY 19,1995 PSA#1350NASA, John F. Kennedy Space Center, Kennedy Space Center, FL 32899 Z -- PRESOLICITATION - REHABILITATE BUILDING M7-505 HVAC AND ROOF -
PHASE I SOL IFB 10-95-0039 DUE 070695 POC Jack Massey, Contracting
Officer, OP-ESO-A, 407-867-7230. The work to be performed consists of
providing all management, labor, equipment and materils to Rehabilitate
Building M7-505 HVAC and Roof - Phase I, Kennedy Space Center. The
project scope requires the contractor to replace six DX-air
conditioning units with chilled water air handling units at Building
M7-505. Included in the work is asbestos abatement, demolition of
piping, ductwork, new equipment, piping, ductwork, and insulation,
controls and electrical service, and, necessary ancillary work. All
work is to be accomplished in accordance with KSC Drawing 79K33958 and
KSC Specification 79K33959.--Plan to issue sol. pkg. on or about
06/06/95.--Magnitude of project between $250,000 to $500,000.--Period
of performance: 240 calendar days.Point of contact for sol. pkg. Mail
Code: ATS-PROm 407-867-2851 or FAX request 407-867-9187.--All
responsible sources may submit a bid/proposal which shall be considered
by the agency. (0137) Loren Data Corp. http://www.ld.com (SYN# 0206 19950518\Z-0035.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|