COMMERCE BUSINESS DAILY ISSUE OF AUGUST 10,1995 PSA#1407U.S. Army Corps of Engineers, Fort Worth District, P.O. Box 17300, 819
Taylor Street, ATTN: CESWF-CT, Fort Worth, TX 76102-0300 Y -- DOL MAINTENANCE FACILITY, PHASE IV, FORT HOOD, TEXAS SOL
DACA63-95-B-0175 DUE 092595 POC Linda Jones, Contract Specialist,
(817/334-2986). This project is a Small Disadvantaged Business
Set-A-Side. Project includes addition (23,300 s.f.) to the consolidated
shop building. A new composite epair facility (15,5000 s.f.); a
two-company Headquarters (HQ) standard-design fire station (8,400
s.f.); and a one-mile test track are also included. Work also includes
paving; walks; cub and gutters; fencing and gates; parking; storm
drainage; sewage pumping station; information system; and site
improvements. Estimated Cost Range: $5,000,000 to $10,000,000 - - Bid
sets available at $123.50 for half-size and $278.50 for full-size. No
individual sheets of half-size drawings may be purchased. Requests by
mail must include payment in the applicable amount by company check or
money order made payable to F&A Officer USAED FTW and sent to: USACE,
Attn: Room 13A42, Post Office Box 17300, 819 Taylor Street, Fort
Worth, Texas 76102-0300. NO EXPRESS MAIL PROCEDURES WILL BE UTILIZED ON
INITIAL MAILINGS OF PLANS AND SPECIFICATIONS. Requests in person may be
paid by cash. No refund will be made and materials need not be
returned. If project is cancelled or no award is made, cost of plans
and specifications will be refunded only on written request.
Solicitation to be issued on or about 25 Aug 95. Bid opening on or
about 25 Sep 95. Duration of contract 430 days. Bids from all
responsible Small Disdavantaged Businesses' will be considered. SIC
Code for this procurement is 1541, Small Business Size Standard is $17
million. (0220) Loren Data Corp. http://www.ld.com (SYN# 0092 19950809\Y-0005.SOL)
Y - Construction of Structures and Facilities Index Page
|
|