COMMERCE BUSINESS DAILY ISSUE OF OCTOBER 17,1995 PSA#1453Directorate Of Contracting, Oo-Alc 6014 Dogwood Avenue/Bldg 1258, Hill
Air Force Base, Ut 84056-5816 R -- ICBM SOL F42610-96-R-AAAAB POC For copy, Pat
Oliver/Lmke/(801)777-0902, For additional information contact Pat
Oliver/Lmke/(801)777-0902 This advance synopsis is issued for the
purpose of obtaining a Market Survey for the Minuteman III Propulsion
Replacement Program (PRP) Software Upgrade. As part of the MM III ICBM
extension plan, the PRP effort will replace the propellant in three
booster stages. The Flight Program Constant Tape (FPCT) and the
Minuteman Operational Targeting Program (MOTP) software baseline
require corresponding modifications to incorporate the new propellant
performance characteristics and physical properties. It is anticipated
that three separate contracts will be issued for the following: (1)
modification of the Flight Program Constant Tape (FPCT) software; (2)
modification of the Minuteman Operational Targeting Program (MOTP)
software and a Nuclear Safety Cross-Check Analysis (NSCCA) of the
changes to the FPCT software; and, (3) a Nuclear Safety Cross-Check
Analysis (NSCCA) of the changes to the MOTP software. A series of
ongoing system modifications and software changes make it impossible to
provide a final version of the software baselines, simulation tools,
and test beds at this time. These will not be available until after the
first quarter 1998. Therefore, any potential offeror is required to
acquire or develop their own software programs, simulation tools, and
test beds and in addition, the offeror must be able to demonstrate
his/her expertise and knowledge of the Minuteman III weapon system
software to the government at his/her own expense. The offeror must
have had experience within the last three years with the MM III weapon
system and operational software. To prequalify, each potential offeror
must successfully complete a software knowledge and capability
demonstration test. The offeror shall prepare and submit a knowledge
and capability demonstration plan. The plan shall include, but is not
limited to the following: Hardware; provide a list and detailed
description of all simulation tools and test bed hardware suites
acquired which will be used for this effort. Software: provide a list
and detailed description of all software programs acquired to support
the operation of the simulation and test tools acquired. Integrated
Systm: provide a detailed narrative describing the purpose and function
of each of the software programs, simulation tools and test bed suites.
Personnel: provide a detailed narrative for each person involved with
the program, specifically describe his/her software development
experience and/or MM III weapon system experience and the purpose and
function of each person. A demonstration of the software programs,
simulation tools, test beds, and MM III weapon system software will be
scheduled after government acceptance of the plan which shall consist
of the following: a. Demonstrate MM III weapon system knowledge
bycorrectly manipulating and processing all test cases provided by the
government. b. Present concept to demonstrate weapon system
compatibility for all required modifications. c. Provide test approach
that demonstrates end-to-end proof of concept for each test case. d.
Provide rationale for the selection and design of target cases to
verify that the weapon system integrity has not been comprised by the
modified software. e. Describe the objective of each test or operation
and how they will be accomplished. f. Describe the ''set up'' and any
unique requirements for each test or operation. g. Be prepared to
explain and verify any anomalies or errors observed during the
operation or test and their impact upon a successful demonstration. h.
List specification(s) documents required to ascertain pass/fail
criteria for each operation or test. i. Provide for each operation or
test a confidence factor/rating to assist in weapon system accuracy
calculations. It is anticipated that the requests for proposal will be
released in March 1996 with a proposal response due in May 1996. All
responsible, interested offerors should respond to Patricia Oliver,
OO-ALC/LMKE, 6014 Dogwood Avenue, Bldg 1258, Hill AFB, UT 84056-5816 no
later than 20 Oct 95. No telephone or FAX requests. Only written
requests received directly from the requestor are acceptable. The
requestor must respond with a plan for meeting the governments
requirements. (0286) Loren Data Corp. http://www.ld.com (SYN# 0058 19951016\R-0009.SOL)
R - Professional, Administrative and Management Support Services Index Page
|
|