COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 14,1996 PSA#1531USDA, Forest Service, P. O. Box 1270, 100 Reserve Street, Hot Springs,
AR 71902 Z -- SHADY LAKE DAM IMPROVEMENTS SOL RFQ 08-09-96-16 DUE 032296 POC
Contact Point, Fran Harrison, (501)321-5221, Contracting Officer, Gary
S. Baber, (501)321-5204, Additional Contact, Wanette Guthrie,
(501)321-5206 Remove, transport, and unload the existing sluice gate
stem, stem guide, and handwheel gate operator to the Mena Work Center,
Mena, Arkansas; Furnish and install new hydraulic lift system, stem,
stem guide(s), piping, and accessories; install two (2) chain link
gates; modify and install trash racks (furnished by Government) to the
existing inlet structure of dam. The lake will be drained to
accommodate this work. The lake will be lowered beginning on or about
09/03/96. When the lake is empty the work may commence. Measurements
necessary to confirm dimensions or otherwise needed to order material
must be made with the lake full. Work must be completed within 45
calendar days from the date the lake is emptied. Project is located at
the Shady Lake Recreation Area on the Mena Ranger District, Ouachita
National Forest, Polk County, Arkansas. Estimated price range is
$25,000 - $50,000. (0043) Loren Data Corp. http://www.ld.com (SYN# 0112 19960213\Z-0013.SOL)