COMMERCE BUSINESS DAILY ISSUE OF APRIL 10,1996 PSA#1570Department of the Army, New England Division, Corps of Engineers, 424
Trapelo Road, Waltham, Massachusetts 02254-9149 Z -- RECONSTRUCTION OF QUINCY RESERVOIR DAM, BRAINTREE, MASSACHUSETTS
SOL DACW33-96-B-0026 DUE 053096 POC Jerry Nunziato, 617-647-8424 The
work of this project consists of removing Quincy Reservoir Dam Earthen
Embankment, portions of the dam concrete rubble core wall, and the
existing concrete outlet works. Prior to demolition of the existing
dam, the work includes draining the reservoir, preparation of the
reservoir area for the stockpiling of materials, diversion of water,
and construction of haul routes. The new work consists of
reconstructing the dam embankment, a dike, and reconstructing new
outlet works. The work is mainly site work and concrete work. The
concrete work includes massive cast in place structures and pressure
grouting of grout curtains in fractured rock. Related work includes
erosion control, a precast concrete bridge over the spillway and
restoration of areas disturbed during construction. The work will be
phased construction with critical schedule milestones due to flood
hazard risk. Estimated cost of the work is between $5,000,000.00 and
$10,000,000.00. Work shall be completed within 720 calendar days. Plans
and specifications available on or about 042596 at a cost of $30.00 per
set. All responsible sources may submit a bid which will be considered
by the New England Division. (0099) Loren Data Corp. http://www.ld.com (SYN# 0185 19960409\Z-0017.SOL)