COMMERCE BUSINESS DAILY ISSUE OF NOVEMBER 29,1996 PSA#1731U.S.P.F.O. for MA, Contracting, 143 Speen St., Natick MA 01760-2599 Z -- UPGRADE HEATING DISTRIBUTION SYSTEM SOL DAHA19-97-B-0001 DUE
012397 POC William B. Devitt, Contract Specialist, 508-233-5761.
PRE-SOLICITATION: The project covered by this statement consists of
furnishing all plant, labor, supplies, equipment, materials and
transportation for upgrading the heating system for the main aircraft
hangar (Building #15) in accordance with the Plans and Specifications.
The project includes replacing an existing boiler and converting
another boiler to hot water. Heat fixtures and piping will be replaced.
Work involves all associated demolition, some site work, removal of
trench drains and associated electrical work and does include asbestos
removal. Project has critical time parameters as follow: a. Heat
system will not be off prior to 15 April 97, b. Hangar will be
available for use during June 1997. There is one additive bid item for
painting and sealing the hangar floor. All work to be performed at
Barnes Air National Guard Base, Westfield, MA in accordance with the
plans and specifications. Performance period is for 180 days after
receipt of the Notice to proceed. Estimated magnitude of construction
is between $250,000.00 and $500,000.00. Interested parties qualified to
perform work under SIC 1711, Plumbing, Heating and Air Condi-tioning,
should notify this office, in writing, of their intrest in bidding as
the prime contractor. Bid packages are not yet available but
anticipated issue date is on/about 23 DEC 96. (0331) Loren Data Corp. http://www.ld.com (SYN# 0099 19961127\Z-0012.SOL)