COMMERCE BUSINESS DAILY ISSUE OF APRIL 1,1997 PSA#1814U.S. SPECIAL OPERATIONS COMMAND ATTN: AMSAT-D-TK 4300 GOODFELLOW W
BLVD. ST. LOUIS, MO 63120-1798 J -- OVERHAUL OF COMPONENTS ON THE MD-500 SERIES AIRCRAFT. SOL
USZA95-97-R-0017 DUE 042997 POC Point of Contact: Robert S. Blaine,
Contract Specialist, Phone: 314-263-0857, Fax: 314-263-1828, E-mail:
bblaine@tapo1.tapo.stl.army.mil Contracting Officer, Richard J. Cooney,
314-263-2279 Overhaul of components for McDonnell Douglas Helicopter
Systems (MDHS) MD-500 series helicopters. This procurement is a 100%
Small Business Set-Aside. All parts used in the overhaul of these items
must be new MDHS parts. All work must be conducted in accordance with
the MDHS service manual. The work must be performed in accordance with
all Federal Aviation Administration Regulations. This procurement will
be evaluated for multiple awards, one award for each contract line item
number (CLIN). The following terms and conditions apply to all CLINs:
Quantity, the quantity will be identified on each delivery order.
Inspection and Acceptance will be Origin, the contractors facility.
F.O.B. will be Destination, the contractor will include the shipping
costs in their proposed unit price. The destination will be identified
on each delivery order, the normal delivery will be to: MSSA/CRP HHC
160th SOAR (ABN), Attn: Property Book Officer, Bldg. 7262, Hangar 15,
Ft. Campbell, KY 42223-5000. The tu rn around time for the items is 30
days after receipt of the item by the contractor. Packing and
Packaging will be best commercial practice. The firm fixed price
overhaul and the over and above work shall not exceed 50% of thets
procurement cost for the item, this is the Maintenance Expenditure
Limit (MEL). The MEL shall be calculated as follows: 50% of the MDHS
current catalog price. The Economic Price Adjustment is limited to 10%
of the offerd price over the 3 yr. term of hte contract. CLIN 0001
Overhaul PN: 369H1800-501; T/R Pitch Control 0001AA Firm Fixed Price
Overhaul $__ __ __ __ each 0001AB Over and Above work(time and
material) labor $__ ____ per hour parts cost plus __ __ ___% CLIN 0002
Overhaul PN: 369H7010-501; Unilock 0002AA Firm Fixed Price Overhaul
$__ __ __ __ each 0002AB Over and Above work(time and material) labor
$__ ____ per hour parts cost plus __ __ ___% CLIN 0003 Overhaul PN:
369A5350-41; Over Running Clutch 0003AA Firm Fixed Price Overhaul $__
__ __ __ each 0003AB Over and Above work(time and material) labor $__
____ per hour parts cost plus __ __ ___% CLIN 0004 Overhaul PN:
369D26301-231, -251; L/G Damper 0004AA Firm Fixed Price Overhaul $__ __
__ __ each 0004AB Over and Above work(time and material) labor $__ ____
per hour parts cost plus __ __ ___% CLIN 0005 Overhaul PN: 369D24518-3,
-5; N2 Indicator 0005AA Firm Fixed Price Overhaul $_&llmdash; __ __ __
each 0005AB Over and Above work(time and material) labor $__ ____ per
hour parts cost plus __ __ ___% CLIN 0006 Overhaul PN: 369A4514-3;
Engine Power Out 0006AA Firm Fixed Price Overhaul $__ __ __ __ each
0006AB Over and Above work(time and material) labor $__ ____ per hour
parts cost plus __ __ ___% CLIN 0007 Overhaul PN: 369A4516-7; N1
Tachometer 0007AA Firm Fixed Price Overhaul $__ __ __ __ each 0007AB
Over and Above work(time and material) labor $__ ____ per hour parts
cost plus __ __ ___% CLIN 0008 Overhaul PN: 369D21728; T/R Forks 0008AA
Firm Fixed Price Overhaul $__ __ __ __ each 0008AB Over and Above
work(time and material) labor $__ ____ per hour parts cost plus __ __
___% CLIN 0009 Overhaul PN: 369D21800; T/R Pitch Control 0009AA Firm
Fixed Price Overhaul $__ __ __ __ each 0009AB Over and Above work(time
and material) labor $__ ____ per hour parts cost plus __ __ ___% CLIN
0010 Overhaul PN: 369d27611-503, M/R Swash Plate 0010AA Firm Fixed
Price Overhaul $__ __ __ __ each 0010AB Over and Above work(time and
material) labor $__ ____ per hour parts cost plus _&llmdash; __ ___%
CLIN 0011 Overhaul PN: 369D26300-251; L/G Damper 0011AA Firm Fixed
Price Overhaul $__ __ __ __ each 0011AB Over and Above work(time and
material) labor $__ ____ per hour parts cost plus __ __ ___% CLIN 0012
Overhaul PN: 369D28312; Oil Cooler 00121AA Firm Fixed Price Overhaul
$__ __ __ __ each 0012AB Over and Above work(time and material) labor
$__ ____ per hour parts cost plus __ __ ___% CLIN 0013 Overhaul PN:
369H6425-5; Dimmer Control 0013AA Firm Fixed Price Overhaul $__ __ __
__ each 0013AB Over and Above work(time and material) labor $__
&llmdash;___ per hour parts cost plus __ __ ___% CLIN 0014 Overhaul PN:
369A4521-3, -5, -7, -- -9; TOT Indicator 0014AA Firm Fixed Price
Overhaul $__ __ __ __ each 00`4AB Over and Above work(time and
material) labor $__ ____ per hour parts cost plus __ __ ___% The
following Provisions and Clauses Apply: FAR 52.212-3, CONTRACTOR
CERTIFICATIONS; FAR 52.212-4, CONTRACT TERMS AND CONDITIONS --
COMMERCIAL ITEMS ( AUG 1996); FAR 52.212-5, CONTRACT TERMS AND
CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS --
COMMERCIAL ITEMS (AUG 1996); FAR 52.211-5, NEW MATERIALS (MAY 1995);
FAR 52.216-4, ECONOMIC PRICE ADJUSTMENT -- LABOR AND MATERIAL (APR
1984); FAR 52.216-18, ORDERING (OCT 1995); 52.216-21, REQUIREMENT (OCT
1995); 52.219-6, NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (JUL 1996);
52.245-2, GOVERNMENT PROPERTY(FIXED PRICE CONTRACTS)(DEC 1989); DFARS
252.217-7028, OVER AND AABOVE WORK (DEC 1991) (0086) Loren Data Corp. http://www.ld.com (SYN# 0036 19970401\J-0002.SOL)
J - Maintenance, Repair and Rebuilding of Equipment Index Page
|
|