COMMERCE BUSINESS DAILY ISSUE OF DECEMBER 12,1997 PSA#1991USDA-Natural Resources Conservation Service, 101 South Main Street,
Temple, Texas Y -- CONSTRUCTION OF EIGHT EWP SITES, BANDERA COUNTY, TEXAS SOL
NRCS-4-TX-98 DUE 012998 POC James Stautzenberger, (817) 334-5258, Ext.
3507 CONSTRUCTION of Group One, Sites 1-1, 1-7, 1-8, 1-11, 1-13, 2-1,
2-10, and 3-3, Bandera County Emergency Watershed Protection (EWP)
Project, Bandera County, Texas. Estimated quantities of the major items
of work are: Rock Riprap, 1,022 Tons; Grouted Rock Riprap, 404 Cu.Yd.;
Sand Cement Bag Riprap, 432 Sq.Ft.; Pipe, Corrugated Metal, 48" I.D.,
55 Linear Ft.; Pipe, Corrugated Metal, 24" I.D., 25 Linear Ft.; and
Lump Sum Items for Mobilization, Structure Removal, Obstruction
Removal, Clearing, Excavation, and Earthfill. Estimated Price Range is
$100,000.00 to $500,000.00. Performance time is 68 calendar days. All
responsible sources may submit a bid which shall be considered by the
agency. (0344) Loren Data Corp. http://www.ld.com (SYN# 0091 19971212\Y-0005.SOL)