COMMERCE BUSINESS DAILY ISSUE OF JUNE 19,1998 PSA#2120USDI, National Park Service, Point Reyes National Seashore, Point
Reyes, CA 94956 Z -- WATERSHED RESTORATION AT REDWOOD NATIONAL PARK SOL
1443-IB-8530-98-009 POC Kris Swofford, Contracting Officer,
415/663-8522, ext 230 E-MAIL: Click here to request a copy of the
solicitation via, kris_swofford@nps.gov. Furnish all labor, equipment,
materials and supervision necessary to accomplish watershed
restoration of 0.55 miles of the M-Line, 0.22 miles of the M-10, and
0.11 miles of associated spur roads in the hillslope area above Redwood
located between Tom McDonald Creek and Forty Four Creek at Redwood
National Park, approximately 6.5 miles south of the town of Orick,
Humboldt County, CA. The project includes excavating road fill from
stream channels, pulling back side- cast road fill, decompacting roads,
retrieving and burying debris from logging and other activities (cable,
abandoned vehicles, concrete foundations, etc), restoring the
configuration of the pre-disturbed landforms (ridges, stream valleys
and swales) along the road corridors and spreading the organic matter
encountered during excavations on the finished surfaces. The nature of
the work generally requires bulldozers to push fill up steep slopes
and shape/finish slopes while side-hilling, and excavators to excavate
fill and shape/finish slopes while sitting on steep slopes. The
equipment will need to be used on steep terrain and in difficult
working conditions. Access to some work sites, or portions of work
sites, will require operator skill and dexterity to minimize access
impacts over steep irregular ground. The size of excavations associated
with this work can range from less than one hundred cubic yards to
several thousand cubic yards in volume. Heavy equipment work is
typically limited to 50-55 hours per week with at least two days off in
any two week period, and will only be permitted between sunrise and
sunset. It is expected that a Notice to Proceed will be issued
approximately late August 1998 (pending determination of Threatened and
Endangered Species restrictions), requiring the Contractor to start
work within 5 days of receipt, and complete all base bid items within
90 days thereafter. The estimated price range of the base bid and all
optional bid items is between $100,000 and $250,000. The Invitation for
Bid will become available in early July with bids due 30 days after
issuance. Interested parties may submit a written request for
solicitation to the attention of the Contracting Officer at the Point
Reyes address above or by facsimile to 415/663-8132. All responsible
sources may submit a bid and will be considered. (0168) Loren Data Corp. http://www.ld.com (SYN# 0142 19980619\Z-0007.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|