COMMERCE BUSINESS DAILY ISSUE OF JULY 24,1998 PSA#2144Willamette National Forest, 211 E. 7th, Eugene, Oregon, 97401 Y -- QUENTIN CREEK SLIDE STABILIZATION-BLUE RIVER RANGER DISTRICT. SOL
SOL R6-18-98-112 DUE 092398 POC Contact Contract Specialist. Telephone
No. 541/465-6506 A project for Quentin Creek Slide Stabilization. Work
consists of drainage improvement and excavation, horizontal drains,
controlled compacted fill (geocomposite drain, welded wire forms and
geogrid). Project is located on the Blue River Ranger District,
Willamette National Forest, Lane County Oregon. Estimated start work
date is July 15, 1999. Contract performance time is 90 calendar days.
Government's estimate is between S250,000 and S500,000. This contract
is NOT set-aside for small business pursuant to Public Law 100-656,
Small Business Competitive Demonstration Act. Posted 07/22/98
(I-SN226839). (0203) Loren Data Corp. http://www.ld.com (SYN# 0127 19980724\Y-0011.SOL)
Y - Construction of Structures and Facilities Index Page
|
|