COMMERCE BUSINESS DAILY ISSUE OF AUGUST 4,1998 PSA#2151Gila River Indian Community, Property Section, PO Box 97, 315 Casa
Blanco Road, Sacaton, Arizona 85247 Y -- INSTALLATION OF CONCRETE PRESSURE PIPE SOL MM- IC DUE 090898 POC
Larry Sinclair, Project Manager or Charley Johnson, Construction
Engineer (520)562-3301 The Gila River Indian Community (GRIC) is
requesting sealed bids from General Contractors for the construction of
a segment of Pima-Maricopa Irrigation Project (P-MIP) water
distribution system, located on the GRIC Reservation along Pecos Road
from 56th street to east of Kyrene Road in Maricopa County. This 1.566
miles of pipeline project is commonly known as "Memorial Area
Pipeline, Reach MM-IC" and consists of underground installation of 84"
diameter (8150 ft.), 54" diameter (1371 ft.), and 36" diameter(70 ft.)
concrete pressure pipe including 6 manholes, 6 air/vacuum valves and a
36" knife gate. This installation also requires removing and replacing
1110 ft. of existing fence. The project duration is 240 days, with
estimated start date on September 21, 1998. Price range is $1,000,000
to $5,000,000. Bidding Documents, including Plans and Specifications,
may be purchased by making payment of $200 (non-refundable) to the
Tribal Cashier located in Tribal Council Ke at the SW corner Pima and
Main Streets, Sacaton, Arizona. Bid documents may then be picked up at
the P-MIP Project Office located in the Land and Waater Resources
Building, Room 200, 192 Skill Center Road, Sacaton, Arizona. Issue Date
is August 7, 1998. Bid Documents may be viewed at the Sacaton Public
Library, corner Church and Main Streets, Sacaton, Arizona. There will
be a Pre-bid Conference on August 19, 1998 at 9:00 am at the P-MIP
Project Office. Bids are due on September 8, 1998 at 2:00 pm (MST) and
shall be returned in sealed envelope clearly marked "Memorial Area
Pipeline, reach MM-IC" to Connie Huenergardt at P.O. Box 97, 315 West
Casa Blanca Road, Sacaton, Arizona. Bid Opening will be at 2:30 pm,
following closing time, at the P-MIP Project Office. Each bid shall be
accompanied by a 10% Bid Bond. All bidders are to comply with GRIC
regulations and policies, including Community member preference in
employment and Indian-owned business preference as established by the
GRIC. An award shall be made to an Indian-owned, economic enterprise,
if its' bid is within 10% of the lowest bid. Posted 07/31/98
(W-SN231157). (0212) Loren Data Corp. http://www.ld.com (SYN# 0155 19980804\Y-0012.SOL)
Y - Construction of Structures and Facilities Index Page
|
|