COMMERCE BUSINESS DAILY ISSUE OF AUGUST 14,1998 PSA#2159Lake Meredith National Recreational Area, P.O. Box 1460, Fritch, TX
79036 Y -- CONSTRUCTION OF STRUCTURES & FACILITIES SOL 1443RQ754098004 DUE
092598 POC Diane Van Tatenhove 806-857-0311 Fax: 806-857-0311 Build
equipment pole barns in the maintenance yard at Lake Meredith National
Recreation Area, Fritch, TX. This will be a 3 tier project consisting
of separate bid items for each tier. Each tier will be completed or
not contingent upon available funding. Tier one (1) -- This work is to
complete the construction of an equipment shed, closed on three sides,
using building materials and construction methods which will match the
existing equipment shed. The building is to be 28' deep by 160' long.
The shed roof will be approximately 12'8" at the back and 14'8" at the
front. Tier two (2) -- This work is to complete the construction of an
equipment shed, closed on three sides, using building materials and
construction methods which will match the existing equipment shed. The
building is to be 28" deep by 120' long. The shed roof will be
approximately 12'8" at the back and 14'8" at the front. Tier three (3)
-- This work is to complete the construction of an equipment shed,
closed on three sides, using building materials and construction
methods which will match the existing equipment shed. The building is
to be 28' deep by 180' long. The shed roof will be approximately 12'8"
at the back and 14'8" at the front. List of materials types: --
Support members are to be 4 X 4 steel and will be set in 2' of
concrete. -- Rafter trusses are to be 8" steel I-beams. -- Roof purlins
are to be 2" X 6" C channel. -- Wall bracing will be 2" X 6" C channel
-- The covering must be 26 gauge R panel with 20 year sand colored
paint warranty in matching sand color. Posted 08/12/98 (W-SN235905).
(0224) Loren Data Corp. http://www.ld.com (SYN# 0136 19980814\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|