COMMERCE BUSINESS DAILY ISSUE OF SEPTEMBER 2,1998 PSA#2172GSA, PBS, NCR, Property Development Division (WPC), Room 2002, 7th & D
Streets, SW, Washington, DC 20407 Y -- FDA CONSOLIDATION -- CFSAN & CVM, COLLEGE PARK, MD SOL
GS-11P98AQC0011 DUE 103098 POC Harry Debes, Project Manager, or Bonnie
Echoles, Contracting Officer, (202)708-7623 E-MAIL: FDA CONSOLIDATION
-- CFSAN/CVM, COLLEGE PARK, MD, bonnie.echoles@gsa.gov or
harry.debes@gsa.gov. The General Services Administration (GSA) hereby
notifies of the intent to issue a Request for Proposal (RFP) in a
negotiated procurement for the Construction of the Food and Drug
Administration -- Center for Food Safety and Applied Nutrition
(FDA-CFSAN) Superstructure. Construction is for a five (5) story
superstructure. One of the five levels is below grade. Overall, the
building will have over 260,000 occupiable square feet (24,760 osm)
with a total of over 410,000 gross square feet (38,000 gsm). Unique
features of the project include 100,000 gsf (9,290 gsm) laboratories
and approximately 250,000 gsf of modern offices, and 60,000 gsf (5,575
gsm) of longterm filing, classrooms, exercise room, and a loading dock
area. The building includes a four (4) story atrium, a 5,000 gsf food
court building and a state-of-the-art physical security. The project
will be constructed in two (2) phases, consisting of foundations and
below grade structures by a current construction contract and the
remainder of the superstructure in this construction procurement. A
construction contract for the foundation phase was awarded to Hillian
Brothers and Sons, Inc. Work started on April 27, 1998 and is scheduled
to be completed by December 30, 1998. This superstructure procurement
is scheduled to be awarded in November 1998 with on-site construction
starting December 1998, and overall project completion scheduled for
April 2001. Posted 08/31/98 (W-SN243885). (0243) Loren Data Corp. http://www.ld.com (SYN# 0129 19980902\Y-0007.SOL)