COMMERCE BUSINESS DAILY ISSUE OF NOVEMBER 22,1999 PSA#2480U. S. Army Corps of Engineers, Omaha District, 215 North 17th Street,
Omaha, NE 68102-4978 Y -- CONSTRUCTION SERVICES KC-135 APRON EXTENSION-PHASE 1, GRAND FORKS
AFB, ND SOL DACA45-00-B-0002 DUE 011900 POC Kevin McElroy (402)221-4108
for technical; Jim Brasch (402)221-4916 WEB: Omaha District Advertised
Solicitations, http://ebs.nwo.usace.army.mil/ebs/contract.htm. E-MAIL:
Kevin P. McElroy, Kevin.P.Mcelroy@usace.army.mil. Solicitation No.
DACA45-00-B-0002,On or about 15 December 1999, this office will issue
Invitation for Bids for the construction of KC-135 APRON
EXTENSION-PHASE I, GRANDFORKS AFB, ND. Bids will be opened on or about
19 January 2000. THIS SOLICITATION IS RESTRICTED TO SMALL BUSINESS
PARTICIPATION ONLY. A site visit has been scheduled on 05 January 2000.
Contractors interested in attending the site visit should contact the
Grand Forks Resident Engineer, U.S. Army Corps of Engineers, 7th &
Holzapple, Bldg. 214, Grand Forks AFB, Telephone: (701) 594-5016/5575.
FAX (701) 594-5526. DO NOT submit requests for plans and
specifications to the site visit personnel listed above. See "Ordering"
below. THE WORK WILL INCLUDE THE FOLLOWING: This project consists of
extending the KC-135 parking apron with new infrastructure to support
assigned aircraft. Project includes adding KC-135R parking spaces,
installing JP-8 fuel piping to fuel outlet/refueling pits, relocating
existing fuel isolation and maintenance vaults, and installing water
lines and fire hydrants. (APPROX. QUANTITIES) Sawcut 2" asphalt
pavement: 300 LF, Sawcut 24" concrete pavement: 190 LF, Remove 2"
asphalt pavement: 7,528 SY, Remove 24" concrete pavement: 60 SY,
Install 3" asphalt pavement: 6,000 SY, Install 12" reinforced concrete
pavement: 55,600 SY, Remove 36" RCP storm drain line: 640 LF, Install
6" subdrain pipe: 4,400 LF, Install 15" RCP up to 42" RCP storm drain
lines: 2,000 LF, Remove 12" stainless steel fuel pipe: 640 LF, Install
12" stainless steel fuel pipe: 3,735 LF, Install 8 hydrant fuel pits,
Install 4 concrete isolation vaults w/valves and rolling pit lids,
Remove 1 concrete isolation vault w/valves and rolling pit lid. Site
utility work includes new exterior lighting, electrical manholes, and
communication lines. Earthwork includes cut and fill and removing
46,000 CY of excess soil, and seeding the disturbed areas. The
estimated construction cost of this project is between $7,500,000 and
$10,000,000. Contractor's Quality Control will bea requirement in this
contract. The Contractor will be required to commence work within 10
days after notice to proceed and complete the work 540 calendar days
after receipt of Notice to Proceed. Provisions will be included for
liquidated damages in case of failure to complete the work in the time
allowed. Performance and payment bonds will be required. The plans and
specifications are available on Compact Disk (CD-ROM) and will be
provided free of charge. It has been determined that the number of
Compact Disks be limited to one (1) per firm. Plans and Specifications
will not be provided in a printed hard copy format. Contractors may
view and/or download this project from the Internet at the following
Internet address: http://ebs.nwo.usace.army.mil/ebs/contract.htm,
Advertised Solicitations.asp. Ordering of CD-ROM shall be made through
the Internet address above. To register on the Omaha District website,
go to the "Solicitation Registration" section of the synopsis and click
on the link for "Registering". If you do not have Internet access, then
you may fax your request to (402) 221-4530, faxed requests will take
longer to process, causing a delay in receiving Solicitation documents.
Please include the following information: 1) Name of Firm; 2)Point of
Contact; 3) Mailing Address; 4) Street Address for Parcel Delivery
Service; 5)Telephone and Fax Phone Numbers with Area Code (FAX numbers
are mandatory to ensure the receipt of any amendments that may be
faxed); 6) Levelof Participation (General Contractor, Subcontractor,
Supplier or Plan Room); and 7) Large Business, Small Business or Small
Disadvantaged Business. If any of the information changes during the
advertisement period, submit the information via e-mail to
Kevin.P.McElroy@usace.army.mil or by written request or fax. Failure to
provide the above information and any changes may cause a delay in
receiving the CD-ROM and amendments. Questions regarding the ordering
of the same should be made to: 402-221-4108. Telephone calls regarding
Small Business matters should be made to: 402-221-4110. Telephone
calls on contents of drawings and specifications should be made to
Specification Section at: (402) 221-4413. Commander U.S. Army Engineer
District, Omaha, ATTENTION: CENWO-CT-S, 215 North 17th Street, Omaha,
NE 68102-4978. "SEE NOTE 1". Posted 11/18/99 (W-SN401898). (0322) Loren Data Corp. http://www.ld.com (SYN# 0101 19991122\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|